Alkalizing & Roasting Project

Customer : ADM Cocoa Pte Ltd
Year : 2005-2006
Contract Type : Mechanical Installation

This project was to upgrade the existing alkalizing & roasting facility by adding 1 unit of Conditioner and 1 unit of Roaster at the existing plant.

As main contractor for this project, we installed the Conditioner & Roaster supplied by the specialist contractor from UK. Major lifts involving 400 ton & 500 ton cranes tandem lifting of Roaster & Conditioner (3m diameter x 23m length) through existing plant roof 33m.